Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Kootenay-Columbia MP urges end to ‘illegal roadblocks’ in solidarity with pipeline dispute

Rob Morrison says protestors across Canada need to remove roadblocks on roads, rail lines

New ‘hub’ model takes regional approach to doctor recruitment in West Kootenay

Kootenay-Boundary a provincial leader in effectively attracting doctors to work here

The Musical Life of Marlene Nash

Pictured above: Marlene Nash re-enacts one of her winning numbers from the… Continue reading

Town of Creston gets grant to ‘undevelop’ reservoir site

By Lorne Eckersley A last minute grant application earlier in the winter… Continue reading

Organic waste pick-up expected by 2022 in RDCK

But there are many unanswered questions in Nelson about cost and details

VIDEO: B.C. senior recalls ‘crazy’ wartime decision to grab bear cub from den

Henry Martens – now 96 – says he was lucky to be alive after youthful decision to enter a bear’s den

Cheapest in B.C.: Penticton gas prices dip below $1 per litre

Two stores in Penticton have gas below a dollar.

Loans or gifts? Judge rules woman must pay B.C. man back $7K

B.C. judge rules that woman must pay back more than $7,000 in advanced funds to man

VIDEO: Outpouring of worldwide support for bullied Australian boy

Australian actor Hugh Jackman said ‘you are stronger than you know, mate’

‘A horror show:’ Ex-employee shares experience at problematic Chilliwack seniors’ home

Workers are paid below industry standard at all Retirement Concepts facilities

Forest industry protests northern B.C. caribou protection deal

B.C. Mining Association supports federal-Indigenous plan

Youth-led report calls on B.C. government to create plan to end youth homelessness

There are no dedicated programs for youth homelessness at federal, provincial level, report says

Trudeau: Time for blockades to end and Indigenous leaders to work with government

Prime minister says situation in Coastal GasLink pipeline dispute is ‘unacceptable and untenable’

RCMP clarifies stance on removing officers from Wet’suwet’en territory in northern B.C.

Police say will remove officers only if hereditary chiefs keep road open to pipeline workers

Most Read